1、深化设计阶段(BIM+4D技术+物联网技术应用)
![现场实测实量1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304548-3502b324bd74702ac3191d99b90d10ec.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![现场实测实量2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304549-57a1577693e23229474e04f00a5a0c48.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![BIM模型构建1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304549-786904d038343eb35170edf501b80943.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![BIM模型构建2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304549-37cf9a6f7d80a071faa71d7fa43db3bc.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![3D扫描数据建立建筑模型.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304549-6a5a731b546d50687a6833f570234049.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![建立设备BIM族库,排布机房设备位置.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304549-f4ba263abcb76abb17a58382a25e6d11.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![根据管综排布,优化管道路由,绘制机房全专业管道模型.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304550-8577cd9422873017066ae3ff7d4e3c78.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![确定支架安全形式及位置.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304550-85c1aac7f35f3cf8aa34e78edabd64f4.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
2、工厂化预制
![生产图绘制4.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304550-4e1e9e3fc4c8318b6faf9b37e4a2774d.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![生产图绘制1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304550-c0b45210c72979cbf310f9e70c194efb.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![生产图绘制2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304551-7564a43bd8107bc6510e5243ba30c482.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![生产图绘制3.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304551-433d91b0add13508233ed935277cc871.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![管材下料1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304551-6af110f325ba000293027337e55a33f0.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![管材下料2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304551-725441933462070abb7d26399c736a0d.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![组对焊接1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304551-92f499d897d54c42a9964810b75eb88a.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![组对焊接2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-3114c4c5b3504a15b699960fbe69ca43.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![防腐与试装2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-4e0c0855eac785e458301f9af19487ed.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![防腐与试装1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-9904705d1ba3454e971c000537ebbdff.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
3、物料运输管理
![物料运输1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-17f4172124841abd83679e1bddeda268.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![物料运输2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-943933c2359c1739686bdd2dd23e33ee.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![物料运输3.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-2dd6e7b665ee006164552b97671b1947.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![物料跟踪1.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-45ae0eb87f012a9fe0fb72022db54af3.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![物料跟踪2.jpg 472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304552-64c72a63f47bf2c2962c217c20744940.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
4、装配安装
5、BIM技术应用及装配式机房公司内部推广交流学习
![472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304553-09b94360abe1d1837196cbb90d1e78e4.png?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
![472㎡机房,40个小时完成组装!首个地源热泵装配式机房惊艳亮相!视频来看施工全过程](https://source.coyis.com/wp-content/uploads/2022/01/1641304553-b866a559a8938c92f046249a6d5f4136.jpeg?x-oss-process=image/resize,w_1600/interlace,1/quality,Q_100)
来源:中建八局三公司
如有侵权,请联系删除
1、深化设计阶段(BIM+4D技术+物联网技术应用)
冷冻水循环泵模块
冷确水循环泵模块
主机前段模块
2、工厂化预制
3、物料运输管理
4、装配安装
5、BIM技术应用及装配式机房公司内部推广交流学习